Tender review meeting with Contracts Director and Estimator prior to tender submission

Project Handover Meeting - Internal with CM/PM/Estimator

Attend client pre-start meeting

Review and authorise for signature official client orders

Issue joinery quantities to suppliers for pricing (update quotes from pre-contract as required)

Issue ceiling quantities to procurement for pricing (update quotes from pre-contract as required)

Agree prelim expenditure with PM/CM prior to commencement of project

Monitor expenditure periodically throughout duration of project

Procure labour only Sub Contractors as chosen by CM

Procure supply & fix Sub Contractors

Arrange and attend Sub-contractor pre-start meeting

Ensure insurances are up to date and valid

Issue Sub-Contractor Evaluation Form & Self Billing Document

Update sub-contrcators CSA periodically

Obtain all necessary RAMS etc from supply & fix sub-contractors and submit to client for approval prior to commencement on site

Attend design meetings as necessary and monitor any arising variations

Issue and monitor RFI's

Review Drawing Revisions Prior To External Release & Evaluate Costs

Price Client Variations

Review Site Audit reports and issue associated costs to client

Issue notice to commence to sub-contractors

Issue notice of delay to sub-contractors when required

Issue clean up notices to sub-contractors when required

Cash Flow Projector

Apply Value Engineering

CVR Submission

Monthly CVR Meeting (Includes Production Input)

Monthly Sub Contractor Valuation

Raise & Issue Sub Contract Payment Notices

Instruct Sub Contractor Variations as they occur and prior to commencement.

Make any recorded contra charges / deductions

Verify Day Work Sheets Issued By Sub-Contractors

Valuation Of Day work Sheets

Sub Contract Final Account

Monthly External Valuation To Client

Final Account Agreement including issuing statement to finance

Issue application for 1/2 retention at PC

Issue application for 1/2 retention following completion of defects (12 months)